Project Timeline

  1. 2026
  2. 2027
  3. 2028
  4. 2029
  5. 2030
  1. Earthworks Sep - Oct Completed
  2. R/C Works Oct - May In progress
  3. MEP Works Dec - Dec Planned
  4. Shell & Core Works Feb - Nov Planned
  5. Elevators Aug - Apr Planned
  6. Facade Works Feb - Mar Planned
  7. B6-B7 Bridge, Metal Works Aug - Apr Planned
  8. Fit Out Works Feb - Jul Planned
  9. Landscaping & Vertical Planning Works Feb - Jul Planned